chilled water
July 24, 2006 at 1:43 pm | sam | everyday science, newsThe chilled water system at Stanford has been basically down for the last month and—now that the weather is getting ridiculously hot—we’re on the brink of the apocalypse. We can’t run our big lasers because they need to be cooled by the chilled water and the temperature in the offices and some of the labs it approaching hott with two “t”s. I mean, my office is in the basement and I’m sweating; the offices upstairs and in Mudd building are much warmer than outside (where the temperature is 90 F).
Thankfully, the most essential locations on campus (like the hospital) still get chilled water routed to them. Also, LINX, a for-profit cafeteria on the first floor of the BioX building, still is nice and cool. Thank god!
Check out this link for more cool (ha!) facts.
2 Comments »
RSS feed for comments on this post. TrackBack URI
Leave a comment
Powered by WordPress, Theme Based on "Pool" by Borja Fernandez
Entries and comments feeds.
Valid XHTML and CSS.
^Top^
Below are some emails (note the name of the sender):
.
July 22, 2006
.
Colleagues,
.
I’m sending this follow up message to you at Bob Reidy’s request. My
original message from June 22 is included below for your reference.
Here is an update on the situation since that last communication:
.
Chilled Water capacity continues to be extremely limited. A temporary
chilled water plant has been constructed on Roble Field to add nearly
3000 additional tonshich has helped us avoid additional curtailment
measures. Overnight, we took delivery of additional equipment and
now have an additional 400 tons of cooling on line at that site. We
have vendors searching for additional equipment throughout the
country and will install more equipment as it becomes available.
.
The recent heat wave has extended over multiple days without
sufficient relief to rebuild our ice storage needed to meet peak
campus demand. In order to save chilled water for hospital use and
critical research processes, on Friday nearly 30 buildings were
curtailed, or partially curtailed, where chilled water is used
primarily for comfort cooling. In other buildings throughout the
campus, temperatures in buildings have been set higher than
previously.
.
The Central Energy plant chilled water project is not expected to be
fully complete until the end of September. Some improvements are
scheduled to be complete in early August, which will allow for
increased chilled water capacity. However, recent long-range weather
forecasts indicate that the summer and fall temperatures will be the
hotter than previous years. This means we expect to have additional
periods of curtailment throughout this time.
.
We will do everything possible to minimize the impact to your
programs that depend on chilled water. Facilities Operations Zone
Management staff will continue to stay in regular communications with
your building managers to address building concerns.
.
We very much appreciate your help and cooperation during this crisis.
.
Thank you.
.
Chris Christofferson
Associate Vice Provost for Facilities
.
.
June 22, 2006
.
Colleagues,
.
I’m sending this message to you at Bob Reidy’s request.
.
As you may be aware, the University has had a shortage of chilled water
since the start of the heat wave last Friday, June 16th. We implemented a
Chilled Water curtailment over Commencement weekend while being sensitive
to Commencement-related activities. Chilled Water capacity remains
extremely limited because of a continuing construction project in the
Central Energy Facility.
.
What we’ve done so far:
.
In order to meet critical peak demands, chilled water temperatures have
been slightly elevated throughout campus during the week, heating systems
have been turned off, and comfort cooling has been reduced where possible
to save chilled water for critical processes and hospital use. As a
result of curtailing building preheating in the early morning hours,
some areas may actually be colder than usual early in the morning and
warmer in the afternoon.
.
Next steps:
.
We expect some relief from the hot weather this weekend and possibly next
week. In the meantime, we have arranged for the installation of
supplemental cooling in the form of a temporary chilled water plant
on Roble Field. Our plan is to have an additional 1,000 tons of
cooling in place by Monday morning, and an additional 2,000 tons in
place by next Friday. As this additional cooling becomes available
and temperatures stabilize, we will gradually phase out of the
curtailment. We have a committment from the vendor that this
equipment will remain in place as long as it is needed.
.
In the meantime, Facility Operations Zone Management staff will stay
in regular communications with your building managers, addressing
their concerns as they arise and continuing to be sensitive to both
research requirements and scheduled events in the buildings.
.
Thank you for your patience and understanding.
.
Chris Christofferson
Associate Vice Provost for Facilities
Comment by sam — July 24, 2006 #
haha sucka. fayer lab has a private chiller. not too bad for our lasers yet…
thanks mike!
Comment by ilya — July 24, 2006 #